Week 41-44
11/1/20262 min read
Unfortunately, it seems to have become a habit for me to leave long gaps between updates. I'll try to do better!
We have started a complete apartment renovation, which is very welcome, as it means quite a lot of work ahead.
First, we demolished all the internal walls, ceilings and tiled floors, as there were several layers of flooring in some areas. This generated a huge amount of demolition waste. We ended up filling four or five containers, although I honestly can't remember the exact number. On top of that, we also filled four 1m³ bags, as one load-bearing wall could not be demolished until it had been properly supported by a steel beam.
Once all the demolition work was completed, we applied self-levelling compound to the floors to achieve the same floor level throughout the apartment, or at least a much better result than before.
We are now working on the framework for the new walls, as well as installing framing and insulation on all the internal surfaces of the apartment. This is to improve the walls and provide insulation against heat, cold and noise.
The air conditioning ducts have been installed in all the ceilings, along with both the indoor and outdoor units.
The windows that need to be relocated or changed in size have been removed so that the bricklayer can carry out the necessary alterations. Insulation work is now underway, and electrical wiring will begin before we can start plasterboarding.
Regarding previous quotations, there has been no response from several potential customers, so I think we can probably forget about those!
One customer has been looking at a different type of window, so that quotation needs to be revised and sent again.
There was also an emergency call-out to a customer whose property I look after through my keyholding service. The customer's daughter and her friends had arrived at the holiday apartment but couldn't get the door unlocked. After a bit of fiddling around with lock lubricant and a crowbar, we eventually managed to get them inside. Just to be clear, there was no damage to the door and we didn't have to force it open! I will take the lock apart and investigate what went wrong to make sure it doesn't happen again.
As for the ongoing saga with the café, I have assembled all the counters, wrapped the drawers in vinyl and stained and varnished all the wooden surfaces. I have also assembled some of the stainless steel fittings, as I'm getting tired of seeing them just lying around.
Believe it or not, a new electrician is actually on the way! However, they are waiting for new approved documentation required by Iberdrola, the electricity company. The documents previously submitted were not acceptable, so everything has had to be sorted out again.
There is finally a little hope, although I am still doubtful that the café will open this year. More than a year has now passed since the premises became available, and many months have been spent waiting for the electrical installation to be completed. But we remain hopeful!
I went there on Friday to remove all our tools, as there was a risk of riots in central Valencia on Saturday. Thankfully, it seems that all the violence was avoided, but I didn't want to take any unnecessary risks.
We have also taken on another smaller job, which is scheduled to start next week, at least the first part of it. A customer wants a steel entrance door installed. Five internal doors will also need to be fitted at a later stage.