Week 46

11/15/20262 min read

Earlier this week, we installed a steel entrance door for a customer who is building a new house. It took considerably longer than expected because the structure that the prefabricated steel door frame was supposed to be fitted into was not properly constructed. The steel used was a little too light, and the frame was not sufficiently secured, so the overall stability left quite a bit to be desired. However, the customer will need to discuss this with the contractor responsible for that part of the construction and have it rectified, as this was not included in our scope of work.

As for the apartment renovation, all the walls have now been plasterboarded, apart from the front-facing walls. This was because we were waiting for the delivery of the new windows, which have now arrived. We have also started filling and smoothing the walls in preparation for painting.

The plumber and electrician have completed all the internal installations, so all the bathroom walls are now in place as well. We purchased the floor tiles for the bathrooms, along with the necessary materials for laying them. This means the tiler can now get started too. We have also begun installing the framework for the suspended ceilings.

A considerable amount of time this week was also spent clearing out two storage rooms that were absolutely packed with belongings. It was quite a job and required two full containers to get everything removed.

Thursday morning was spent sitting in considerably longer traffic queues on the motorway than usual. There had been a strike the previous day, which had resulted in the port being closed, so all the lorries were heading there once operations resumed. There was quite a lot of sitting around in traffic, followed by taking alternative routes just to get where we needed to go.

We finished Friday by applying waterproofing in the shower areas and installing three windows.

I also managed to sort out the lock for the customer who had trouble getting into their property a couple of weeks ago. I took the lock apart, cleaned and lubricated it, and made a small adjustment to the strike plate in the door frame. It is now working perfectly again.

Bandelin Construction

Construction company with over 35 years of renovation experience.

Phone & Email

bandelinconstruction@gmail.com

Carrer del General Llorens, 8, Investelia, Benicalap, 46025, Valencia

+34 665 73 27 97

+46 73 626 18 68

© 2024. All rights reserved.